expansion project update text superimposed over a photo of the front of the library

Why does the Library need an expansion?

The 1913 building lacks space and flexibility for the future. Space for patrons in every age group, space for programs, space for staff, and space for collections is needed.

Why now?

Massachusetts Board of Library Commissioners does not offer the Massachusetts Public Library Construction Program (MPLCP) grant every year. We submitted a letter of intent in 2023, applied in 2024, won but was waitlisted, and are now eligible for the state funds. Libraries today and in the future have different needs than libraries built in 1913. 

What will the expansion add?

Services through dedicated spaces: enclosed children and teen rooms, event rooms, reservable meeting & study rooms, workspace for staff, more collection space and parking. Much needed electrical, technology, roof, and infrastructure repairs are also included in the project.

What will the expansion retain?

The wood, carvings, front lawn, granite facade, front entrance, spiral staircase, front lobby, and reading rooms.

What will the expansion remove but repurpose in the new building?

The back stacks and marble floor. The marble may be used in the facade for the new side entrance and the iron stacks may be repurposed as interior artwork.

Where is it expanding to?

The WSL Board of Trustees purchased the properties at 24, 28 & 30 Cottage St with the specific purpose of expanding the library’s footprint in the back.

How much will it cost?

The estimate for total project costs is $31.9 million. To date, $250,000 has been spent explicitly on this project. 

How will it be paid for?

The MPLCP grant covers 45.65% of eligible costs at an estimated $12.5 million. Funding from Northbridge taxpayers through a debt exclusion, which goes away once paid off, the WSL private endowment, fundraising, and donations will contribute to the remaining costs. 

What is the timeline?

  • May 4, 2027: Spring town meeting 
  • May 18, 2027: Spring election
  • Sept 2028: Break ground
  • Feb 2030: Grand Reopening

What happens if the votes fail?

The town will forfeit the grant and the funds will go to another town that is on the waitlist. Northbridge can apply again the next time this competitive grant is offered but funds already invested will not be recouped.

For more information about the building expansion project and to view the plans please visit https://whitinsvillelibrary.org/expansion